Master Body

2. Project Direction Overview

The starting bespeak in discussing how projects should be properly managed is to kickoff sympathize what a project is and, just as importantly, what it is not.

People accept been undertaking projects since the primeval days of organized human activity. The hunting parties of our prehistoric ancestors were projects, for example; they were temporary undertakings directed at the goal of obtaining meat for the customs. Large complex projects accept also been with us for a long time. The pyramids and the Great Wall of People's republic of china were in their twenty-four hours of roughly the same dimensions equally the Apollo project to transport men to the moon. We utilise the term "project" oftentimes in our daily conversations. A husband, for example may tell his wife, "My main project for this weekend is to straighten out the garage." Going hunting, edifice pyramids, and fixing faucets all share certain features that make them projects.

Project Attributes

A project has distinctive attributes that distinguish information technology from ongoing work or business operations. Projects are temporary in nature. They are not an everyday business concern process and take definitive start dates and end dates. This characteristic is important because a big office of the project effort is defended to ensuring that the project is completed at the appointed fourth dimension. To do this, schedules are created showing when tasks should begin and stop. Projects can last minutes, hours, days, weeks, months, or years.

Projects exist to bring about a product or service that hasn't existed earlier. In this sense, a project is unique. Unique means that this is new; this has never been done before. Mayhap it's been done in a very similar style before but never exactly in this way. For example, Ford Motor Company is in the concern of designing and assembling cars. Each model that Ford designs and produces can be considered a projection. The models differ from each other in their features and are marketed to people with various needs. An SUV serves a dissimilar purpose and clientele than a luxury car. The blueprint and marketing of these two models are unique projects. Even so, the actual associates of the cars is considered an operation (i.e., a repetitive process that is followed for most makes and models).

In contrast with projects, operations are ongoing and repetitive. They involve work that is continuous without an ending date and with the aforementioned processes repeated to produce the same results. The purpose of operations is to keep the arrangement operation while the purpose of a project is to meet its goals and conclude. Therefore, operations are ongoing while projects are unique and temporary.

A project is completed when its goals and objectives are accomplished. It is these goals that drive the projection, and all the planning and implementation efforts undertaken to attain them. Sometimes projects end when it is determined that the goals and objectives cannot be accomplished or when the production or service of the project is no longer needed and the projection is cancelled.

Definition of a Project

There are many written definitions of a project. All of them contain the cardinal elements described higher up. For those looking for a formal definition of a projection, the Project Management Institute (PMI) defines a projection as a temporary try undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite starting time and end. The stop is reached when the project'south objectives have been achieved or when the project is terminated because its objectives will not or cannot be met, or when the need for the project no longer exists.

Projection Characteristics

When considering whether or not you have a project on your hands, there are some things to keep in mind. Starting time, is it a project or an ongoing operation? 2d, if information technology is a project, who are the stakeholders? And third, what characteristics distinguish this endeavor as a project?

Projects have several characteristics:

  • Projects are unique.
  • Projects are temporary in nature and have a definite kickoff and catastrophe date.
  • Projects are completed when the project goals are achieved or it's determined the project is no longer viable.

A successful project is one that meets or exceeds the expectations of the stakeholders.

Consider the post-obit scenario: The vice-president (VP) of marketing approaches you lot with a fabulous idea. (Apparently it must be "fabulous" because he idea of it.) He wants to set up kiosks in local grocery stores as mini-offices. These offices volition offering customers the power to sign up for automobile and home insurance services as well as make their bill payments. He believes that the exposure in grocery stores will increment awareness of the company'south offerings. He told you that senior management has already cleared the project, and he'll dedicate as many resources to this as he tin can. He wants the new kiosks in place in 12 selected stores in a major metropolis by the terminate of the twelvemonth. Finally, he has assigned you to caput up this projection.

Your get-go question should be, "Is it a project?" This may seem elementary, merely disruptive projects with ongoing operations happens frequently. Projects are temporary in nature, have definite start and end dates, outcome in the creation of a unique product or service, and are completed when their goals and objectives accept been met and signed off by the stakeholders.

Using these criteria, permit's examine the assignment from the VP of marketing to determine if it is a project:

  • Is it unique? Aye, considering the kiosks don't exist in the local grocery stores. This is a new way of offer the visitor'south services to its customer base. While the service the visitor is offering isn't new, the way it is presenting its services is.
  • Does the product have a limited timeframe? Yeah, the showtime date of this project is today, and the cease date is the cease of side by side year. It is a temporary endeavor.
  • Is there a manner to determine when the projection is completed? Yes, the kiosks will exist installed and the services will be offered from them. Once all the kiosks are installed and operating, the projection volition come up to a close.
  • Is in that location a mode to decide stakeholder satisfaction? Yeah, the expectations of the stakeholders volition be documented in the form of requirements during the planning processes. These requirements will be compared to the finished product to determine if it meets the expectations of the stakeholder.

If the answer is yeah to all these questions, then we have a project.

The Process of Project Direction

You've adamant that you lot have a project. What now? The notes you scribbled downward on the back of the napkin at luncheon are a commencement, but not exactly good project management practice. Too often, organizations follow Nike's communication when it comes to managing projects when they "just do it." An assignment is fabricated, and the project team members jump directly into the development of the product or service requested. In the terminate, the delivered product doesn't meet the expectations of the client. Unfortunately, many projects follow this poorly constructed path, and that is a primary contributor to a big percentage of projects not meeting their original objectives, every bit divers by performance, schedule, and budget.

In the United States, more than $250 billion is spent each yr on it (It) application evolution in approximately 175,000 projects. The Standish Group (a Boston-based leader in project and value performance research) released the summary version of their 2009 CHAOS Report that tracks project failure rates across a broad range of companies and industries (Figure two.1).

A bar chart showing 32% of projects succeeding, 44% challenged, and 24% failed
Figure 2.one: Summary of 2009 Standish Group CHAOS report.

Jim Johnson, chairman of the Standish Group, has stated that "this twelvemonth'southward results testify a marked decrease in projection success rates, with 32% of all projects succeeding which are delivered on time, on budget, with required features and functions, 44% were challenged-which are tardily, over upkeep, and/or with less than the required features and functions and 24% failed which are cancelled prior to completion or delivered and never used."

When are companies going to stop wasting billions of dollars on failed projects? The vast majority of this waste material is completely avoidable: simply get the right business needs (requirements) understood early in the procedure and ensure that project management techniques are applied and followed, and the project activities are monitored.

Applying skillful project management subject area is the fashion to help reduce the risks. Having good project direction skills does not completely eliminate problems, risks, or surprises. The value of skilful project management is that you take standard processes in place to bargain with all contingencies.

Project management is the awarding of noesis, skills, tools, and techniques applied to project activities in lodge to see the project requirements. Project management is a procedure that includes planning, putting the project plan into action, and measuring progress and functioning.

Managing a projection includes identifying your project's requirements and writing down what everyone needs from the project. What are the objectives for your project? When everyone understands the goal, it'southward much easier to keep them all on the right path. Make sure you set goals that everyone agrees on to avoid team conflicts afterward on. Understanding and addressing the needs of everyone affected by the project means the end effect of your project is far more probable to satisfy your stakeholders. Last merely not least, equally project manager, you will too exist balancing the many competing project constraints.

On whatever project, you will have a number of project constraints that are competing for your attention. They are cost, scope, quality, risk, resource, and time.

  • Toll is the budget approved for the project including all necessary expenses needed to deliver the project. Inside organizations, project managers have to residue between not running out of money and not underspending considering many projects receive funds or grants that accept contract clauses with a "utilize it or lose it" arroyo to project funds. Poorly executed budget plans tin consequence in a last-minute rush to spend the allocated funds. For virtually all projects, cost is ultimately a limiting constraint; few projects can go over budget without eventually requiring a corrective action.
  • Scope is what the project is trying to achieve. Information technology entails all the piece of work involved in delivering the project outcomes and the processes used to produce them. It is the reason and the purpose of the projection.
  • Quality is a combination of the standards and criteria to which the project's products must be delivered for them to perform finer. The product must perform to provide the functionality expected, solve the identified trouble, and evangelize the benefit and value expected. It must likewise meet other functioning requirements, or service levels, such equally availability, reliability, and maintainability, and have adequate finish and shine. Quality on a project is controlled through quality assurance (QA), which is the process of evaluating overall project functioning on a regular footing to provide confidence that the project will satisfy the relevant quality standards.
  • Risk is defined by potential external events that will have a negative impact on your project if they occur. Risk refers to the combination of the probability the event volition occur and the bear upon on the project if the event occurs. If the combination of the probability of the occurrence and the bear on on the project is as well loftier, you should identify the potential event as a risk and put a proactive plan in place to manage the risk.
  • Resources are required to acquit out the project tasks. They can exist people, equipment, facilities, funding, or annihilation else capable of definition (usually other than labour) required for the completion of a project action.
  • Time is defined as the time to complete the project. Time is often the most frequent projection oversight in developing projects. This is reflected in missed deadlines and incomplete deliverables. Proper command of the schedule requires the careful identification of tasks to be performed and authentic estimations of their durations, the sequence in which they are going to be done, and how people and other resource are to be allocated. Whatever schedule should take into account vacations and holidays.

You may take heard of the term "triple constraint," which traditionally consisted of only time, price, and scope. These are the primary competing project constraints that y'all have to exist near aware of. The triple constraint is illustrated in the course of a triangle to visualize the project piece of work and see the relationship between the telescopic/quality, schedule/time, and cost/resources (Figure 2.2). In this triangle, each side represents one of the constraints (or related constraints) wherein any changes to any one side cause a change in the other sides. The all-time projects have a perfectly balanced triangle. Maintaining this balance is difficult because projects are prone to change. For case, if scope increases, cost and fourth dimension may increase disproportionately. Alternatively, if the amount of coin yous accept for your project decreases, you lot may be able to do as much, but your time may increase.

""
Effigy 2.2: A schematic of the triple constraint triangle.

Your project may have boosted constraints that you lot must face, and as the project manager, you lot accept to balance the needs of these constraints against the needs of the stakeholders and your project goals. For instance, if your sponsor wants to add functionality to the original scope, you will very probable need more money to terminate the projection, or if they cutting the upkeep, you will have to reduce the quality of your scope, and if you don't get the advisable resources to work on your project tasks, y'all volition have to extend your schedule because the resource y'all have take much longer to finish the piece of work.

You get the idea; the constraints are all dependent on each other. Think of all of these constraints as the classic carnival game of Whac-a-mole (Figure 2.3). Each time you try to push 1 mole back in the pigsty, another one pops out. The best communication is to rely on your project team to go along these moles in place.

whac a mole machine
Effigy 2.3: Whac-a-mole.

Here is an example of a project that cut quality because the projection costs were fixed. The P-36 oil platform (Effigy 2.four) was the largest basis production platform in the world capable of processing 180,000 barrels of oil per twenty-four hour period and five.2 million cubic metres of gas per 24-hour interval. Located in the Roncador Field, Campos Basin, Brazil, the P-36 was operated by Petrobras.

Petrobras P-36 Sinking
Effigy 2.four.: The Petrobras P-36 oil platform sinking.

In March 2001, the P-36 was producing around 84,000 barrels of oil and 1.3 1000000 cubic metres of gas per twenty-four hours when it became destabilized by two explosions and subsequently sank in iii,900 feet of water with 1,650 curt tons of crude oil remaining on lath, killing 11 people. The sinking is attributed to a complete failure in quality assurance, and pressure for increased production led to corners being cutting on safety procedures. It is listed as one of the most expensive accidents with a price tag of $515,000,000.

The following quotes are from a Petrobras executive, citing the benefits of cut quality assurance and inspection costs on the project.

"Petrobras has established new global benchmarks for the generation of exceptional share­holder wealth through an aggressive and innovative plan of price cutting on its P36 production facility."

"Conventional constraints have been successfully challenged and replaced with new paradigms appropriate to the globalized corporate market place."

"Emptying of these unnecessary straitjackets has empowered the project's suppliers and contractors to propose highly economical solutions, with the win-win bonus of enhanced profitability margins for themselves."

"The P36 platform shows the shape of things to come in the unregulated global market economy of the 21st century."

The dynamic trade-offs between the project constraint values accept been humorously and accurately described in Figure 2.5.

A sign. Image description available.
Effigy 2.v: Good, Quick, Cheap: Choose ii. A sign seen at an automotive repair store. [Image Description]

Project Management Expertise

In order for you, as the project manager, to manage the competing project constraints and the project as a whole, at that place are some areas of expertise you should bring to the project squad (Figure ii.xi). They are knowledge of the awarding area and the standards and regulations in your industry, agreement of the projection environment, general management noesis and skills, and interpersonal skills. It should be noted that industry expertise is non in a certain field but the expertise to run the project. So while knowledge of the type of industry is important, you will have a project team supporting you in this effort. For example, if you are managing a projection that is edifice an oil platform, you would not be expected to take a detailed understanding of the engineering since your team will have mechanical and civil engineers who volition provide the appropriate expertise; however, it would definitely aid if you understood this blazon of work.

Permit's have a await at each of these areas in more than detail.

Application knowledge

By standards, we mean guidelines or preferred approaches that are non necessarily mandatory. In contrast, when referring to regulations nosotros mean mandatory rules that must be followed, such as regime-imposed requirements through laws. It should become without proverb that as a professional, y'all're required to follow all applicative laws and rules that apply to your industry, arrangement, or projection. Every industry has standards and regulations. Knowing which ones bear upon your project before you begin work will not simply aid the project to unfold smoothly, but will also allow for effective risk analysis.

Areas of expertise: application knowledge, standards & regulations; understanding the project environment; management knowledge & skills; & interpersonal skills
Figure 2.6: Areas of expertise that a project manager should bring to the projection squad.

Some projects require specific skills in certain application areas. Awarding areas are made up of categories of projects that have common elements. They can be divers by industry group (pharmaceutical, financial, etc.), department (accounting, marketing, legal, etc.), engineering (software evolution, engineering, etc), or direction specialties (procurement, research and development, etc.). These application areas are normally concerned with disciplines, regulations, and the specific needs of the project, the client, or the industry. For case, most government agencies take specific procurement rules that apply to their projects that wouldn't be applicable in the construction industry. The pharmaceutical industry is interested in regulations set up forth by government regulators, whereas the automotive industry has little or no concern for either of these types of regulations. You need to stay up-to-date regarding your industry and then that you can apply your knowledge effectively. Today's fast-paced advances tin can leave you behind fairly quickly if y'all don't stay abreast of current trends.

Having some level of experience in the application area you're working in volition give yous an advantage when it comes to project direction. While you lot tin can phone call in experts who take the application area noesis, it doesn't hurt for you lot to understand the specific aspects of the awarding areas of your project.

Understanding the Project Surroundings

In that location are many factors that need to be understood within your project environment (Figure 2.7). At one level, you need to retrieve in terms of the cultural and social environments (i.e., people, demographics, and education). The international and political environment is where you need to understand most different countries' cultural influences. Then nosotros move to the physical surround; here we think about time zones. Retrieve about different countries and how differently your project will be executed whether it is just in your country or if it involves an international project squad that is distributed throughout the world in 5 dissimilar countries.

Consider the cultural, social, international, political, and physical environments of a project
Figure 2.7: The of import factors to consider within the project surround.

Of all the factors, the physical ones are the easiest to understand, and it is the cultural and international factors that are often misunderstood or ignored. How we bargain with clients, customers, or project members from other countries tin can be critical to the success of the project. For example, the culture of the United States values accomplishments and individualism. Americans tend to exist breezy and telephone call each other past commencement names, even if having simply met. Europeans tend to be more formal, using surnames instead of first names in a business concern setting, even if they know each other well. In addition, their communication style is more formal than in the The states, and while they tend to value individualism, they also value history, bureaucracy, and loyalty. The Japanese, on the other hand, tend to communicate indirectly and consider themselves part of a group, non as individuals. The Japanese value hard work and success, as most of united states do.

How a production is received can be very dependent on the international cultural differences. For example, in the 1990s, when many large American and European telecommunications companies were cultivating new markets in Asia, their customer'southward cultural differences often produced unexpected situations. Western companies planned their telephone systems to work the aforementioned way in Asia as they did in Europe and the United States. Just the protocol of conversation was different. Call-waiting, a popular feature in the West, is considered impolite in some parts of Asia. This cultural corrigendum could have been avoided had the team captured the project surround requirements and involved the client.

It is oft the simplest things that can cause trouble since, unsurprisingly, in different countries, people practice things differently. Ane of the most notorious examples of this is too one of the about elementary: date formats. What day and month is 2/8/2009? Of course information technology depends where you come from; in North America it is February 8th while in Europe (and much of the rest of the globe) it is 2d August. Clearly, when schedules and deadlines are being defined it is important that anybody is clear on the format used.

The diverseness of practices and cultures and its touch on products in general and on software in particular goes well beyond the date issue. You may be managing a project to create a new website for a visitor that sells products worldwide. There are language and presentation style problems to have into consideration; converting the site into different languages isn't enough. It is obvious that you need to ensure the translation is correct; still, the presentation layer will accept its own prepare of requirements for different cultures. The left side of a website may be the offset focus of attention for a Canadian; the correct side would exist the initial focus for anyone from the Middle Due east, every bit both Arabic and Hebrew are written from right to left. Colors also have different meanings in different cultures. White, which is a sign of purity in North America (due east.g., a helpmate'due south wedding dress), and thus would be a favoured groundwork colour in North America, signifies decease in Japan (due east.g., a burial shroud). Table two.ane summarizes unlike meanings of mutual colours.

Table 2.1: The meaning of colours in various cultures.
Colour U.s. China Japan Egypt France
Red Danger, stop Happiness Anger, danger Decease Aristocracy
Blue Sadness, melancholy Heavens, clouds Villainy Virtue, faith, truth Freedom, peace
Green Novice, amateur Ming dynasty, heavens Future, youth, energy Fertility, strength Misdeed
Yellow Cowardice Birth, wealth Grace, nobility Happiness, prosperity Temporary
White Purity Death, purity Death Joy Naturality

Projection managers in multicultural projects must appreciate the culture dimensions and endeavour to learn relevant customs, courtesies, and business concern protocols before taking responsibility for managing an international projection. A project director must take into consideration these diverse cultural influences and how they may impact the project'south completion, schedule, scope, and cost.

Management Knowledge and Skills

As the project manager, yous have to rely on your project direction knowledge and your general manage­ment skills. Hither, nosotros are thinking of items similar your ability to plan the project, execute it properly, and of form command it and bring it to a successful conclusion, along with your ability to guide the project squad to achieve project objectives and residue project constraints.

There is more to project management than but getting the work done. Inherent in the process of project management are the general management skills that allow the project manager to complete the projection with some level of efficiency and control. In some respects, managing a projection is similar to running a business organization: at that place are risk and rewards, finance and bookkeeping activities, human resource problems, fourth dimension management, stress management, and a purpose for the project to exist. Full general management skills are needed in every projection.

Interpersonal Skills

Last but not least y'all also accept to bring the ability into the project to manage personal relationships and deal with personnel issues as they arise. Here were talking about your interpersonal skills every bit shown in Effigy 2.eight.

Advice

Projection managers spend ninety% of their fourth dimension communicating. Therefore they must be good communicators, promoting articulate, unambiguous exchange of data. Every bit a project managing director, information technology is your job to keep a number of people well informed. It is essential that your projection staff know what is expected of them: what they accept to do, when they have to do information technology, and what budget and time constraints and quality specifications they are working toward. If projection staff members practise not know what their tasks are, or how to attain them, then the entire projection volition grind to a halt. If you exercise not know what the projection staff is (or ofttimes is not) doing, and so y'all volition be unable to monitor projection progress. Finally, if you are uncertain of what the customer expects of you, and then the projection will not even go off the footing. Project advice can thus be summed upwardly as knowing "who needs what information and when" and making sure they have it.

Interpersonal skills include communication, influence, leadership, motivation, negotiation, and problem solving
Figure 2.8: Interpersonal skills required of a project manager.

All projects require audio communication plans, but not all projects volition take the same types of commu­nication or the same methods for distributing the information. For example, will data be distributed via mail or email, is there a shared website, or are face-to-face meetings required? The communication management plan documents how the communication needs of the stakeholders will exist met, including the types of data that will be communicated, who volition communicate them, and who will receive them; the methods used to communicate; the timing and frequency of communication; the method for updating the plan as the projection progresses, including the escalation process; and a glossary of mutual terms.

Influence

Project management is near getting things done. Every system is different in its policies, modes of operations, and underlying civilisation. There are political alliances, differing motivations, alien interests, and ability struggles. A project manager must empathize all of the unspoken influences at piece of work within an organization.

Leadership

Leadership is the ability to motivate and inspire individuals to work toward expected results. Leaders inspire vision and rally people around common goals. A skillful project manager tin can motivate and inspire the project squad to see the vision and value of the project. The projection manager every bit a leader can inspire the project team to discover a solution to overcome perceived obstacles to get the work washed.

Motivation

Motivation helps people piece of work more efficiently and produce better results. Motivation is a constant process that the project managing director must guide to help the team move toward completion with passion and a profound reason to consummate the work. Motivating the team is accomplished by using a variety of team-building techniques and exercises. Team building is but getting a diverse group of people to work together in the most efficient and constructive mode possible. This may involve management events likewise every bit individual deportment designed to meliorate team performance.

Recognition and rewards are an important part of squad motivations. They are formal ways of recognizing and promoting desirable behaviour and are about constructive when carried out by the management team and the project manager. Consider private preferences and cultural differences when using rewards and recognition. Some people don't like to be recognized in forepart of a group; others thrive on it.

Negotiation

Project managers must negotiate for the good of the projection. In any project, the projection managing director, the project sponsor, and the project team will have to negotiate with stakeholders, vendors, and customers to reach a level of agreement acceptable to all parties involved in the negotiation process.

Problem Solving

Problem solving is the ability to understand the heart of a problem, look for a viable solution, and then make a decision to implement that solution. The starting point for problem solving is problem definition. Trouble definition is the ability to understand the cause and event of the problem; this centres on root-cause analysis. If a project manager treats just the symptoms of a problem rather than its cause, the symptoms volition perpetuate and continue through the project life. Even worse, treating a symptom may upshot in a greater problem. For example, increasing the ampere rating of a fuse in your car considering the one-time one keeps blowing does not solve the problem of an electrical short that could result in a burn. Root-crusade analysis looks beyond the firsthand symptoms to the cause of the symptoms, which then affords opportunities for solutions. Once the root of a trouble has been identified, a conclusion must be made to effectively address the problem.

Solutions can be presented from vendors, the project team, the project manager, or various stakeholders. A viable solution focuses on more than just the problem; it looks at the cause and effect of the solution itself. In improver, a timely decision is needed or the window of opportunity may laissez passer and so a new determination will be needed to address the problem. As in near cases, the worst matter you can exercise is nothing.

All of these interpersonal skills will be used in all areas of project direction. Showtime practicing at present because it's guaranteed that you'll need these skills on your next projection.

Paradigm Descriptions

Effigy ii.5 image clarification: The sign says, "We tin can do good, quick, and cheap work. You can take any two simply not all three. 1. Good, quick work won't exist cheap. 2. Expert, cheap work won't be quick. 3. Quick, cheap work won't exist practiced." [Render to Figure 2.v]

Text Attributions

  • This chapter of Project Management is a derivative of Project Direction past Merrie Barron and Andrew Barron. © CC Past (Attribution).
  • Tabular array 2.one: Adjusted from P. Russo and S. Boor, How Fluent is Your Interface? Designing for International Users, Proceedings of the Collaborate '93 and CHI '93, Association for Computing Machinery, Inc. (1993). Table from Barron & Barron Projection Management for Scientists and Engineers, Source: Project Direction for Scientists and Engineers by Merrie Barron; Andrew R. Barron

slaterdialletrem.blogspot.com

Source: https://opentextbc.ca/projectmanagement/chapter/chapter-2-what-is-a-project-project-management/